Monday, March 30, 2015

NISPOM Based Certification Questions.

Try these NISPOM based questions. They could complement your ISP Certification or SPeD certification study. See how you do.

1. Disclosure of U.S. Information to Foreign Governments is
guided by the:
a. CSA
b. GCA 
c. COR
d. ITAR
e. Exports Agreements

2. What is the required FCL a contractor facility must have if in possession of only NATO RESTRICTED information?
a. TOP SECRET
b. SECRET
c. CONFIDENTIAL
d. RESTRICTED
e. None of the Above

3. Which of the following are eligibility requirements a company must meet before it can be processed for an FCL?
a. The company must be an organization of at least 25
people
b. The company must have a desire for classified access
c. The company must have a reputation for integrity
d. The company must make its bottom line for three
consecutive quarters
e. The company is the only entity that can perform the work

4. When can a contractor disclose classified information to
another contractor?
a. Furtherance of contract 
b. Furtherance of business development
c. When directed by FSO
d. When directed by CSA
e. Just as long as other contractor is cleared




Scroll down for answers:






1. Disclosure of U.S. Information to Foreign Governments is
guided by the:
a. CSA
b. GCA (NISPOM 10-200)
c. COR
d. ITAR
e. Exports Agreements

2. What is the required FCL a contractor facility must have if in possession of only NATO RESTRICTED information?
a. TOP SECRET
b. SECRET
c. CONFIDENTIAL
d. RESTRICTED
e. None of the Above (NISPOM 10-702)

3. Which of the following are eligibility requirements a company must meet before it can be processed for an FCL?
a. The company must be an organization of at least 25
people
b. The company must have a desire for classified access
c. The company must have a reputation for integrity
(NISPOM 2-102c)
d. The company must make its bottom line for three
consecutive quarters
e. The company is the only entity that can perform the work

4. When can a contractor disclose classified information to
another contractor?
a. Furtherance of contract (NISPOM 5-509)
b. Furtherance of business development
c. When directed by FSO
d. When directed by CSA
e. Just as long as other contractor is cleared